Pampa Energía Wind Farm IV (‘PEPE IV’)
PEPE IV, originally an expansion of PEPE III (Pampa Energía Wind Farm III), is located in Coronel Rosales, on national route No. 3, 45 km from the City of Bahía Blanca, Province of Buenos Aires. Four out of 18 V-150 Vestas wind turbines (4.5 MW) were commissioned on December 29, 2022. Other four wind turbines were commissioned on February 25, 2023 (totaling 36 MW). Each wind turbine has a 105-meter hub height, with a 63% load factor of P50. Full commissioning (+45 MW) is expected for the second quarter of 2023.
Technical Data
Plant | Unit | Installed Capacity(MW) | Estimated Start-Up | Type of Unit |
PEPE IV | – | 81 | 1st quarter of 2023 | 18 wind generators |