
Pampa Energía Wind Farm II (‘PEPE II’)
PEPE II is located next to PEMC (Wind Farm Engineer Mario Cebreiro), it is made up of 14 V-136 Vestas wind turbines, each with a 3.8 MW power capacity and a 120-meter hub height. PEPE II’s total installed capacity amounts to 53 MW, which represents 0.1% of Argentina’s installed capacity. It was commissioned on May 10, 2019, selling its energy in the Renewable Energy Term Market (‘MAT ER’). From its commissioning and during 2019, PEPE II generated 122 GWh, which represents an approximate 40% dispatch factor.
The following chart shows certain relevant statistical data on PEPE II:
2019 | |
Net Generation (GWh) | 122 |
Purchases of Energy (GWh) | 7 |
Total Energy Sales (GWh) | 129 |
Average Price (US$/MWh) | 62 |
Average Gross Profit (US$/MWh) | 53 |
Note: Gross Margin before depreciation and amortization, values expressed in nominal terms. AR$/US$ exchange rate: 2018 – 28.13; 2019 – 48.23.
Technical Data
Plant | Unit | Installed Capacity(MW) | Start-Up | Type of Unit |
PEPE II | PAMEEO | 53 | 2019 | 14 wind generators |