May 2019: Commercial Commissioning of the Wind Farms for a Total Power Capacity of 106.4 MW
Commercial commissioning of the Pampa Energía Wind Farm (‘PEPE’) II and III with an installed capacity of 53.2 MW each.

May 2019: Joint Awarding of Ensenada de Barragán Thermal Power Plant
Pampa and YPF jointly acquired the Ensenada de Barragán thermal power plant with a power capacity of 560 MW and a project to close the cycle in order to increase its capacity to 840 MW.
June 2019: Commissioning of Gas Turbine at Genelba Thermal Power Plant
Commercial commissioning to the Gas Turbine 04 for 188 MW and capacity increase of the already existing Gas Turbine 03, Genelba Plus, for additional 19 MW, as part of the Genelba Plus’s closing to combined cycle project.